In short: Every home in Dayton Valley drains to Lyon County's Rolling A treatment plant, and every owner pays the county's sewer bill. Treated effluent waters the golf course in warm months; the rest of the year it goes to the Aspen Creek Rapid Infiltration Basins. Those basins, built in 2022–2023 for about $7 million, were found in 2024 to work at a quarter of their design, which briefly stopped all new building in Dayton. Sewer capacity is a deciding factor for Legacy 49, Silverado's villages and every other development around us.

Start here: Dayton sewer research guide (timeline and sources) · Blog: "The Dayton sewer: a $7 million basin that works at a quarter of its design"

Timeline

Before 2004: the community's tie to the sewer

2004–2008: growth outpaces capacity

2013–2018: septic conversions and planning

2019–2021: "not a guarantee for service"

2022–2023: the basins are built

2024: the building pause

2025–2026: a third of design, and a new director

Open questions

  • Leaks or infiltration in the main sewer lines: no public document found yet.
  • Which bonds the $2,200 "Bond Payments Fee" repays, and any basin cost overruns. A records request to Lyon County would settle both.

People

  • David Bruketta, Lyon County Utilities Director (through mid-2025)
  • Sean Sinclair, Lyon County Utilities Director (by March 2026)
  • Andrew Haskin, Lyon County Manager